RBS and Enterprise Global Template

D

Dan Shepherd

We recently added the RBS to the Enterprise Global Template. Now each time
we access a project it is asking to change the various views, etc. on each
project which is very time consuming. Is there a better way to
populate/publish our changes to ALL projects?
 
M

Mike

We recently added the RBS to the Enterprise Global Template. Now each time
we access a project it is asking to change the various views, etc. on each
project which is very time consuming. Is there a better way to
populate/publish our changes to ALL projects?

Dan

I think you are confused. RBS is a system field and so always exists
within the entrprise global, and changes to it will not impact any
views either in project or pwa. I suspect you have inadvertantly made
local views enterprise views and so when you open a project you get a
clash between the local view and the same-named enterprise view.
Action: close any plans you have open in project; open the enterprise
global and use tools|organiser option to remove any views and tables
you don't want to be enterprise. The remaining views/tables should be
named so that they will not conflict with local values (e.g. prefix
EPM).

regards

Mike
 