M
Marco
Hi,
Here's a subset of our RBS :
---------------------
HQ - Engineering - Equipment - Hardware
- Software
- Systems
- Technology Management - R&D project manager
-
Standardisation
- Operations - Technical project management
---------------------
The project managers are located in the RBS nodes "R&D project manager" and
"Technical project management"
As you can see the project managers have no resources directly "below" them.
The project managers should however be able to build a team and to assign
resources to tasks.
What is here the best approach ? ?
The only solution I have found so far is to set the security such that "All
current and future resources" are available in the Server configuration.
I could also create another RBS with the project managers higher in the tree
but then this does not map anymore to the company's organization chart.
Thanks for any comment.
Marco
Here's a subset of our RBS :
---------------------
HQ - Engineering - Equipment - Hardware
- Software
- Systems
- Technology Management - R&D project manager
-
Standardisation
- Operations - Technical project management
---------------------
The project managers are located in the RBS nodes "R&D project manager" and
"Technical project management"
As you can see the project managers have no resources directly "below" them.
The project managers should however be able to build a team and to assign
resources to tasks.
What is here the best approach ? ?
The only solution I have found so far is to set the security such that "All
current and future resources" are available in the Server configuration.
I could also create another RBS with the project managers higher in the tree
but then this does not map anymore to the company's organization chart.
Thanks for any comment.
Marco