Here's the situation:
We have an RBS that looks something like this:
(Level 1) - Department A
(Level 2) - Department A.Team 1
(Level 3) - Department A.Team 1.Team 1 Resource
The position at Level 2 is currently vacant, so the people at Level 3 are
temporarily reporting to the manager at Level 1. Any updates/changes that
would normally go to the Resource Manager at Level 2 now need to go to the
manager at Level 1 until the position is filled. Since each resource can
have only a single entry in the RBS, how can I implement such a temporary
change in Project Pro / Server 2003?
For the individual projects, I know I can have Level 1 republish with them
being the manager, but I haven't been able to locate any suggestion on how to
make the change the RBS.
What is the best way to update the RBS to support a temporary reporting
structure?
We have an RBS that looks something like this:
(Level 1) - Department A
(Level 2) - Department A.Team 1
(Level 3) - Department A.Team 1.Team 1 Resource
The position at Level 2 is currently vacant, so the people at Level 3 are
temporarily reporting to the manager at Level 1. Any updates/changes that
would normally go to the Resource Manager at Level 2 now need to go to the
manager at Level 1 until the position is filled. Since each resource can
have only a single entry in the RBS, how can I implement such a temporary
change in Project Pro / Server 2003?
For the individual projects, I know I can have Level 1 republish with them
being the manager, but I haven't been able to locate any suggestion on how to
make the change the RBS.
What is the best way to update the RBS to support a temporary reporting
structure?