RBS changes caused reduced access

A

Andres

Greetings all,

I am once again baffled by PS 2002 SP1... we made some changes to the RBS
(moving people around to new structures) and now can no longer see project
information for the users that were moved (i.e. time spent on a task, etc).
We have done this before without any issues so this is new to me.

I have been digging through the tables and trying to identify where the
relationships are created between security, project, and individual but feel
like I'm in an ever changing maze...

Has anyone encountered this behaviour before? Google has been pretty
useless... Anyone have any ideas?

HELP!

Thanks!
 
J

Jim Althoff

Andres,

I'm not an enterprise expert with RBS changes. However, you indicate NEW
RBS codes. I'm wondering if projects need to be republished with the new RBS
structures for them to have knowledge about them. What I mean is that the
references are stored in the database and I'm not sure how project specific
structures are changed unless the project is opened and then saved/published.
Just a guess.
 
A

Andres

I hadn't thought of that so I gave it a try but it still does not work...
thanks for the reply
 