Greetings all,
I am once again baffled by PS 2002 SP1... we made some changes to the RBS
(moving people around to new structures) and now can no longer see project
information for the users that were moved (i.e. time spent on a task, etc).
We have done this before without any issues so this is new to me.
I have been digging through the tables and trying to identify where the
relationships are created between security, project, and individual but feel
like I'm in an ever changing maze...
Has anyone encountered this behaviour before? Google has been pretty
useless... Anyone have any ideas?
HELP!
Thanks!
I am once again baffled by PS 2002 SP1... we made some changes to the RBS
(moving people around to new structures) and now can no longer see project
information for the users that were moved (i.e. time spent on a task, etc).
We have done this before without any issues so this is new to me.
I have been digging through the tables and trying to identify where the
relationships are created between security, project, and individual but feel
like I'm in an ever changing maze...
Has anyone encountered this behaviour before? Google has been pretty
useless... Anyone have any ideas?