B
Bryan
Hi,
I am wondering if the RBS groups define the hierarchy for task updates
in MOPS 2007 as they do in MOPS 2003. For example, if a resource
enters time in a task and submits that update, it will go to their
lead (as defined by the groups in the RBS field). That lead's task
update would go to their manager and so on.
I am not sure if my example is clear, but I am not using timesheets at
all in 2007. My current RBS configuration pretty much mirrors our org
chart.
Any help is greatly appreciated!
I am wondering if the RBS groups define the hierarchy for task updates
in MOPS 2007 as they do in MOPS 2003. For example, if a resource
enters time in a task and submits that update, it will go to their
lead (as defined by the groups in the RBS field). That lead's task
update would go to their manager and so on.
I am not sure if my example is clear, but I am not using timesheets at
all in 2007. My current RBS configuration pretty much mirrors our org
chart.
Any help is greatly appreciated!