In our scenario, project managers may need to include resources
outside of their group in their project, but they do not want project
managers in the other group to change project. Here is a summary of
the problem
I have the following organization:
pm1 1.1
resource1 1.1.1
resource2 1.1.1
pm1 1.2
resource3 1.2.1
resource4 1.2.1
pm1 creates a project (pr1) with resource1 and resource3 and publishes
the assignments. Now pm2 can open pr1 and completely change it and pm1
gets no notification that someone else changed his project.
Has anyone resolved a similar problem?
outside of their group in their project, but they do not want project
managers in the other group to change project. Here is a summary of
the problem
I have the following organization:
pm1 1.1
resource1 1.1.1
resource2 1.1.1
pm1 1.2
resource3 1.2.1
resource4 1.2.1
pm1 creates a project (pr1) with resource1 and resource3 and publishes
the assignments. Now pm2 can open pr1 and completely change it and pm1
gets no notification that someone else changed his project.
Has anyone resolved a similar problem?