B
Bryan A
All,
I have a predicament. I'm 1/2 way through my project when one of the major
summary tasks has to completely revamp their task list and time estimates.
Some of the previous tasks have already either exceeded the baseline work or
have finished early.
If I re-baseline now, the new baseline will change my costs (actual cost &
cost variance). Because the new baseline will contain the new work figures,
this will make my cost the same as my baseline cost therefore giving me a 0
cost variance.
Am I reading this right? How do I now after I've collected actual work and
calculated actual costs do I re-baseline?
thanks for you help!!
Bryan
I have a predicament. I'm 1/2 way through my project when one of the major
summary tasks has to completely revamp their task list and time estimates.
Some of the previous tasks have already either exceeded the baseline work or
have finished early.
If I re-baseline now, the new baseline will change my costs (actual cost &
cost variance). Because the new baseline will contain the new work figures,
this will make my cost the same as my baseline cost therefore giving me a 0
cost variance.
Am I reading this right? How do I now after I've collected actual work and
calculated actual costs do I re-baseline?
thanks for you help!!
Bryan