I have a project with a fixed end date that I have set in Project as a Deadline. If a task slips today, can I tell Project to recalculate the Start and Finish dates for the remaining tasks proportionally? For example, I have a deadline to complete a group of tasks required to organize an Annual conference with many tasks and resources dependent on one another. I have no ability to add resources for budgetary reasons. If one of my tasks slips, then each resource will have less time to complete their remaining work. Using the remaining time between today and the deadline, can Project recalculate the start and end dates for the remaining tasks?