T
The Great Caper
I am using project Server 2003. I have several resources (40 or more)
assigned to many tasks in my plan. When a team member has, say 4 hours a day,
over a week period. The team member updates their time in PWA to reflect the
work they have done. Let's assume it is less then the planned work - 2.5
hours a day. The remaining work is 7.5 hours. How can I get Project Server or
Project Pro to re-forecast the work that did not get done. I was told that
if a team member enters .01 hrs for tasks that were schedueld and they did no
work on it the tool will re-forecast the remaining effort, but this also does
not reforecast effort. Am I doing something wrong, why does PS 2003 not
re-forecast effort?
Thanks,
GC
assigned to many tasks in my plan. When a team member has, say 4 hours a day,
over a week period. The team member updates their time in PWA to reflect the
work they have done. Let's assume it is less then the planned work - 2.5
hours a day. The remaining work is 7.5 hours. How can I get Project Server or
Project Pro to re-forecast the work that did not get done. I was told that
if a team member enters .01 hrs for tasks that were schedueld and they did no
work on it the tool will re-forecast the remaining effort, but this also does
not reforecast effort. Am I doing something wrong, why does PS 2003 not
re-forecast effort?
Thanks,
GC