Re: How do I calculate earliest start time using Microsoft Projects?

J

JulieS

Hello Project confused,

Good news -- you don't have to calculate any of those fields --
Project has already calculated early start, early finish, late
start, late finish as well as total slack (float). Apply the
Schedule table (View Tables > More Tables) to view Late Start, Late
Finish, Free Slack, and Total Slack. You may add Early Start and
Early finish to the table through Insert > Column and scroll the
field list to select the fields you wish to add.,

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Project confused" <Project (e-mail address removed)>
wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top