Re-Publish all task to a specific resource

D

Dale Howard [MVP]

Joe --

You might try the following steps:

1. Open the project in question
2. Click the Filter drop-down list on the Formatting toolbar
3. Select the Using Resource... filter
4. Select the resource in question and then click the OK button
5. Click Collaborate - Publish - Republish Assignments
6. At the top of the dialog, select the "Current view" option from the
drop-down list
7. Click OK

Hope this helps.
 
G

Gary L. Chefetz \(MVP\)

Joe:

Open your project plan and switch to the resource usage view
Select the assignments under the resource you wish to republish
Click Collaborate > Publish > Republish
Make sure that selected items is selected in the pick list in republish
dialog
Viola


--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

-
 