Re-Publish Assignments not working properly.

J

Joe

I have performed a Re-Publish Assignments to get a new field added to the
Timesheets. Specifically, I am trying to add the Baseline Finish Date to the
Timesheet in PWA. I added the column in the view, the column shows up, but
no data is showing up in the PWA view. There is data in the Project Plan.

How can I tell if there is an issue with the Re-Publish Assignments action,
or if there is a server configuration issue?

Any suggestions?

Joe – (from ETS)
 
D

Dale Howard [MVP]

Joe --

You need to add the Baseline Finish field to the list of published fields in
each project using Tools - Customize - Published Fields. After doing this,
then you should republish the assignments using Collaborate - Publish -
Republish Assignments. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top