C
Claudio Hidetoshi
I have to implement the Sub Project_BeforeSafe to get a project custom field
value, entered by the user in Project Summary Task.
Depending of the value, I have to set other four project custom fields'
values.
I have it working in Project Server 2003, but PPS2007 does not suport some
objects used.
I saw many examples using PSI methods to set and get those fields. But I
have to get and set those fields before saving, and the project may not exist
in Project Server database yet.
Thanks,
Cláudio Hidetoshi.
value, entered by the user in Project Summary Task.
Depending of the value, I have to set other four project custom fields'
values.
I have it working in Project Server 2003, but PPS2007 does not suport some
objects used.
I saw many examples using PSI methods to set and get those fields. But I
have to get and set those fields before saving, and the project may not exist
in Project Server database yet.
Thanks,
Cláudio Hidetoshi.