real dates vs baseline dates...

P

Paul

After baselinging a project I had several tasks start
later than planned. How can I refelct the 'true' start
dates when entering work? Should I be using 'task
usage'? Or should I simply use the drop down calendar
box? Is there an easy way to accomplish this?
 
J

Jan De Messemaeker

Hi Paul,

It depends what you want to compare.
If you are only interested in Start and Finish comparisons, insert actual
start and either %complete or actual duration and remaining duration.
If you also want to compare actual work to baseline work, indeed tak usage
is the place. Right-click on the timescale part, click actual work; make ure
to show remaining work in the left part.

Some experimenting will show you how it works.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top