G
ghostme
Hello good pple of the forum, the default max units for a resource in Project
Server is 100%.
Now if I increase the max units of a resource to 200% and assign a task to
th resource the duration reduces to 0.5 days(which is half a day).
Now in a real life scenario how does an increase of the max unit of a
resource affects the availability of that resource.
Thanks
Server is 100%.
Now if I increase the max units of a resource to 200% and assign a task to
th resource the duration reduces to 0.5 days(which is half a day).
Now in a real life scenario how does an increase of the max unit of a
resource affects the availability of that resource.
Thanks