R
robgr
Hello,
I'm trying to find a solution other than the typical grouping method since
it's not giving me quite what I'm looking for.
The situation is that I have several subprojects contained in a master
project. I'm trying to generate a high-level view of the project as well as
grouping information in a meaningful way. The problem is that I'm working in
a Clarity environment and using MSP as the input tool. This makes it
difficult to use certain fields such as Outline codes.
I'd like to find a solution using a text field in which it gives users the
flexibility to arrange tasks in a way that is important to them.
For example assume two different project schedules contained in a master
project: a schedule for Hardware and a schedule for Software. The outline
numbers below are to illustrate the WBS.
1 Hardware
1.1 Prototype A
1.1.1 Design
1.2 Prototype B
1.2.1 Design
2 Software
2.1 Prototype A
2.1.1 Design
2.2 Prototype B
2.2.1 Design
I'd like to rearrange them so that I can eventually get something that looks
like:
1 Prototype A
1.1 HW Design
1.2 SW Design
2 Prototype B
2.1 HW Design
2.2 SW Design
I've tried groups, but I think for my purposes a macro will be the only way
to go. I just need some help getting started with the syntax.
My requirements:
1. Use one text field (can possibly use more if needed)
2. Rearrange and group tasks based on information contained in this text field
Thanks
I'm trying to find a solution other than the typical grouping method since
it's not giving me quite what I'm looking for.
The situation is that I have several subprojects contained in a master
project. I'm trying to generate a high-level view of the project as well as
grouping information in a meaningful way. The problem is that I'm working in
a Clarity environment and using MSP as the input tool. This makes it
difficult to use certain fields such as Outline codes.
I'd like to find a solution using a text field in which it gives users the
flexibility to arrange tasks in a way that is important to them.
For example assume two different project schedules contained in a master
project: a schedule for Hardware and a schedule for Software. The outline
numbers below are to illustrate the WBS.
1 Hardware
1.1 Prototype A
1.1.1 Design
1.2 Prototype B
1.2.1 Design
2 Software
2.1 Prototype A
2.1.1 Design
2.2 Prototype B
2.2.1 Design
I'd like to rearrange them so that I can eventually get something that looks
like:
1 Prototype A
1.1 HW Design
1.2 SW Design
2 Prototype B
2.1 HW Design
2.2 SW Design
I've tried groups, but I think for my purposes a macro will be the only way
to go. I just need some help getting started with the syntax.
My requirements:
1. Use one text field (can possibly use more if needed)
2. Rearrange and group tasks based on information contained in this text field
Thanks