G
Gerardv
Hi,
On
http://office.microsoft.com/en-us/projectserver/HA101020711033.aspx?pid=CH101477241033 I read the following:
If you are a team leader, you can reassign the task to the entire team of
resources, sharing the work equally. If you are not a team leader, tasks can
be reassigned to only one resource. If you need to reassign the task to
multiple resources and you are not the team leader, contact your project
manager.
Has anybody been able to do this? Even as team leader of a team I can only
assign a task to an single individual member of a group. This would be a
helpful feature but I have not been able to figure out how to do this.
Thanks,
Gerard
On
http://office.microsoft.com/en-us/projectserver/HA101020711033.aspx?pid=CH101477241033 I read the following:
If you are a team leader, you can reassign the task to the entire team of
resources, sharing the work equally. If you are not a team leader, tasks can
be reassigned to only one resource. If you need to reassign the task to
multiple resources and you are not the team leader, contact your project
manager.
Has anybody been able to do this? Even as team leader of a team I can only
assign a task to an single individual member of a group. This would be a
helpful feature but I have not been able to figure out how to do this.
Thanks,
Gerard