Hi, PS2007, Infrastructure update and client updates thru Oct 08
Is there an easy way to reassign a resource to another resource quickly?
We have created generic resources (but not marked as generic resources - not
sure why had something to do with showing work outstanding for department,
beside that point..)
They may be scattered through a plan (yes open to doing this on a per plan
basis). They have now hired for this postion and want to change it from TBD
to George. They don't want to have to do it one line at a time.
I tried doing this in Project Pro under a resource view, but still could
only change one task at a time.
Any ideas?
Thanks,
Is there an easy way to reassign a resource to another resource quickly?
We have created generic resources (but not marked as generic resources - not
sure why had something to do with showing work outstanding for department,
beside that point..)
They may be scattered through a plan (yes open to doing this on a per plan
basis). They have now hired for this postion and want to change it from TBD
to George. They don't want to have to do it one line at a time.
I tried doing this in Project Pro under a resource view, but still could
only change one task at a time.
Any ideas?
Thanks,