Reassign from one resource to another with fill or other quick way

L

L8rdays

Hi, PS2007, Infrastructure update and client updates thru Oct 08

Is there an easy way to reassign a resource to another resource quickly?

We have created generic resources (but not marked as generic resources - not
sure why had something to do with showing work outstanding for department,
beside that point..)

They may be scattered through a plan (yes open to doing this on a per plan
basis). They have now hired for this postion and want to change it from TBD
to George. They don't want to have to do it one line at a time.

I tried doing this in Project Pro under a resource view, but still could
only change one task at a time.

Any ideas?

Thanks,
 
D

Dale Howard [MVP]

L8rdays --

Open a project and then click Tools - Build Team from Enterprise. Select
the generic-like resource on the right, a human resource on the left, and
then click the Replace button. That's the fastest way and will replace the
generic-like resource with the human resource on every task to which the
generic-like resource is assigned in the project. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top