Reassign Resources

J

JimS

I am scrubbing schedules submitted by others, and now find they've made a few
mistakes...two resources (one mis-spelled...) that should be all one. How do
I change all the work assigned to resource 47 over to resource 34? I want the
same percentages and all.
 
J

JulieS

HI Jim,

No code needed. Select all tasks in the project, click the assign
resources button. Select Resource 47, click the replace button and
select resource 34 in the Replace dialog.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 