Reauest ability to change view

B

Bill Meacham

I would like to be able to change the view "View task changes submitted by
resources" on the Update page of PWA. I want to change the order of the
columns.
 
D

Dale Howard [MVP]

Bill --

There is no default method available in Project Server to modify the view on
the Updates page. You can "drag and drop" the columns into place, but if
memory serves me correctly, Project Server will restore the original order
of the columns the next time you access this page. Sorry.
 
B

Bill Meacham

Right. I posted this as a suggestion in hopes that it would get to Microsoft
developers or whoever decides on features for the next release. Is this the
appropriate means to do that? If not, what do you suggest?
 
D

Dale Howard [MVP]

Bill --

To let Microsoft know of your desire, I believe you should send an e-mail
message to (e-mail address removed) and put "Project" in the Subject of the
message. Hope this helps.
 