Rebaselining specific tasks

V

verossa

Hi All

The original project baseline was saved on Feb 04. However there was an immediate slip in the project and no work commenced during this month. The first act.work booked was in the month of Mar 04. As a result I want to re-baseline the project to 01 Mar 04 to reflect this slippage

In Task Usage View I'm deleting all the work and baseline data at a resource level for the Feb 04. I then save the baseline for the task only (not the project)

However, I've noticed that the work or baslines deleted in Feb are not automatically redistributed over the remaining duration of the task when re-baseline

Is there a method I can use to do this? I'm not entirely sure I'm making sense so please feel free to ask for clarification

TIA to all who respond - Vers
 
J

James

Good Lord, Verossa, I'm glad you re-attached your brain, otherwise you would have had one heck of a tedious exercise on your hand

I presume that you just changed the project start-date and re-saved the whole project with a new baseline

James :)
 