Hi All
The original project baseline was saved on Feb 04. However there was an immediate slip in the project and no work commenced during this month. The first act.work booked was in the month of Mar 04. As a result I want to re-baseline the project to 01 Mar 04 to reflect this slippage
In Task Usage View I'm deleting all the work and baseline data at a resource level for the Feb 04. I then save the baseline for the task only (not the project)
However, I've noticed that the work or baslines deleted in Feb are not automatically redistributed over the remaining duration of the task when re-baseline
Is there a method I can use to do this? I'm not entirely sure I'm making sense so please feel free to ask for clarification
TIA to all who respond - Vers
The original project baseline was saved on Feb 04. However there was an immediate slip in the project and no work commenced during this month. The first act.work booked was in the month of Mar 04. As a result I want to re-baseline the project to 01 Mar 04 to reflect this slippage
In Task Usage View I'm deleting all the work and baseline data at a resource level for the Feb 04. I then save the baseline for the task only (not the project)
However, I've noticed that the work or baslines deleted in Feb are not automatically redistributed over the remaining duration of the task when re-baseline
Is there a method I can use to do this? I'm not entirely sure I'm making sense so please feel free to ask for clarification
TIA to all who respond - Vers