M
Michael.Tarnowski
Hi community,
we had built a schedule running from 14.04.09 to 25.08.11 from scratch
by paper work. Official project start was 30.05.08.
Now I want to rebuild a backward plan in MSP. I started the task list
with a rack of official agreed MFO-constrained milestones having
predecessor milestone inside the task list. The first task after these
milestones is a milestone called prjStart, at the end is one prjEnd.
All other tasks are between.
In our manually created schedule we estimated the duration and
determined start/end dates by viewing at a calendar; duration are
net work days only.
In MSP I entered all task only by this duration as Fix Duration, non-
effort, FS-linked with 1 full time equivalent assigned. For tracking
reasons I kept the manual start/end dates in two custom date fields
WBS_Start and WBS_End displayed in the Gantt chart.
I assumed that since durations in both schedules are identical, the
MSP scheduled start/end dates will be equal +/- one day with our
manual schedule. But in reality both are differing by month! For
example the first task (which was manually scheduled for 14.4.9)
starts in MSP at 15.08.08!
I know it is in way stupid too rebuild 1:1 a given schedule in MSP and
not let MSP do the planning; but the manual schedule was already
communicated to management before we decided to use MSP for tracking.
I read a lot of books and Internet sources on MSP, especially on the
duration equation. The most obvious approach in MSP is to schedule
forward, estimate and enter task durations, model the dependency
logic, assign generic resources and "accept" the MSP calculated
project end date.
We knew the project end (25.08.11), start of the schedule (14.4.9),
and the logic, as well the duration of each task in between; I agree,
we have no distinct slack.
Our goal is to come up with a schedule to baseline and monitor the
progress in relation to the estimated durations.
Could anybody explain me how I can achieve a MSP schedule in line with
our prior schedule
I appreciate your help very much
Have a nice day
Michael
we had built a schedule running from 14.04.09 to 25.08.11 from scratch
by paper work. Official project start was 30.05.08.
Now I want to rebuild a backward plan in MSP. I started the task list
with a rack of official agreed MFO-constrained milestones having
predecessor milestone inside the task list. The first task after these
milestones is a milestone called prjStart, at the end is one prjEnd.
All other tasks are between.
In our manually created schedule we estimated the duration and
determined start/end dates by viewing at a calendar; duration are
net work days only.
In MSP I entered all task only by this duration as Fix Duration, non-
effort, FS-linked with 1 full time equivalent assigned. For tracking
reasons I kept the manual start/end dates in two custom date fields
WBS_Start and WBS_End displayed in the Gantt chart.
I assumed that since durations in both schedules are identical, the
MSP scheduled start/end dates will be equal +/- one day with our
manual schedule. But in reality both are differing by month! For
example the first task (which was manually scheduled for 14.4.9)
starts in MSP at 15.08.08!
I know it is in way stupid too rebuild 1:1 a given schedule in MSP and
not let MSP do the planning; but the manual schedule was already
communicated to management before we decided to use MSP for tracking.
I read a lot of books and Internet sources on MSP, especially on the
duration equation. The most obvious approach in MSP is to schedule
forward, estimate and enter task durations, model the dependency
logic, assign generic resources and "accept" the MSP calculated
project end date.
We knew the project end (25.08.11), start of the schedule (14.4.9),
and the logic, as well the duration of each task in between; I agree,
we have no distinct slack.
Our goal is to come up with a schedule to baseline and monitor the
progress in relation to the estimated durations.
Could anybody explain me how I can achieve a MSP schedule in line with
our prior schedule
I appreciate your help very much
Have a nice day
Michael