S
Sebastian Cordoba
Hello everyone.
I need to find a way to recalculate EV fields without overwriting an
existing baseline. In order to get it, I've developed a macro to assign a
specific standard rate to the plan's resources ($1/hr) and then assign the
new cost (calculated by Project) to the baseline cost field of each task.
I assumed that all of the EV fields were going to be calculated by Project
as well, but it didn´t happen. Is there a method to do something like:
mytask.BCWS.recalculate()
Thanks for your help.
I need to find a way to recalculate EV fields without overwriting an
existing baseline. In order to get it, I've developed a macro to assign a
specific standard rate to the plan's resources ($1/hr) and then assign the
new cost (calculated by Project) to the baseline cost field of each task.
I assumed that all of the EV fields were going to be calculated by Project
as well, but it didn´t happen. Is there a method to do something like:
mytask.BCWS.recalculate()
Thanks for your help.