N
Nik003
Is there a way to make project recalculate estimated finish date at both task
and project level, based on actuals, work calendar, resource availablity and
remaining time in Project 2007? It's all nice when everything is real-time,
but we need to know how the project finish date gets pushed based on the
actuals from resources.
and project level, based on actuals, work calendar, resource availablity and
remaining time in Project 2007? It's all nice when everything is real-time,
but we need to know how the project finish date gets pushed based on the
actuals from resources.