I
irish_archer68
Hello and thank you for reading this post.
I needed to delete about 100 resources from a project schedule and re-
import the projects with a couple of custom fields populated. There
appears to have been a disconnect between the App server and SQL
server during the process. THe end result is the resources are no
longer visible in PWA, but are visible in the MSP_Resources table in
the Published DB.
When I try to import the 100 resources - using Tools->Enterprise
Options-Imports Resources to Enterprise and receive the message
"Unable to Process Request" error message for every resource.
Has any one ran into this before? If so, was there a graceful way to
reimport or did you need to hand key all resources?
Thank you in advance for any and all replies to this post.
I needed to delete about 100 resources from a project schedule and re-
import the projects with a couple of custom fields populated. There
appears to have been a disconnect between the App server and SQL
server during the process. THe end result is the resources are no
longer visible in PWA, but are visible in the MSP_Resources table in
the Published DB.
When I try to import the 100 resources - using Tools->Enterprise
Options-Imports Resources to Enterprise and receive the message
"Unable to Process Request" error message for every resource.
Has any one ran into this before? If so, was there a graceful way to
reimport or did you need to hand key all resources?
Thank you in advance for any and all replies to this post.