I trying to get to grips with Project but I seem to be
stuck on this one point. I have some tasks that in real
life are running behind schedule, ie 10% of the work has
been completed in 20% of the time. What I want it to do
is to take the uncompleted work from the previous weeks
and add it to the remaining weeks of the task.
In a task of 10 weeks duration at 10 hours/week, I have
just completed the 2nd week but have only achieved 10
hours of work. at the moment it is telling me that I have
got to do 10 hours work last week & 10 hours for the next
8 weeks instead of 11.25 hours for the next 8 weeks.
Any help would be greatly appreciated.
Thanks
I trying to get to grips with Project but I seem to be
stuck on this one point. I have some tasks that in real
life are running behind schedule, ie 10% of the work has
been completed in 20% of the time. What I want it to do
is to take the uncompleted work from the previous weeks
and add it to the remaining weeks of the task.
In a task of 10 weeks duration at 10 hours/week, I have
just completed the 2nd week but have only achieved 10
hours of work. at the moment it is telling me that I have
got to do 10 hours work last week & 10 hours for the next
8 weeks instead of 11.25 hours for the next 8 weeks.
Any help would be greatly appreciated.