A
alex
Hi,
Contexte:
Some resources record hours before the start date or after the finish date.
The impact is the planning is moved according to the new date because actual
is prior to the planning.
I don't use the summary task to record hour but only task.
I don't find any way to correct tis.
The impact is really unexpected.
Each project manager have a rule to auto accept the hours.
each days, around 15 resources updates the hours and the hours should be
apply to the planning. So the project manager don't have to check the hours,
he want to see the actual by reports.
Question
The project manager can't pass the time to check if the resource did a wrong
thing or not.
How can I handle this?
Best regards,
Alexandre BARAULT
Contexte:
Some resources record hours before the start date or after the finish date.
The impact is the planning is moved according to the new date because actual
is prior to the planning.
I don't use the summary task to record hour but only task.
I don't find any way to correct tis.
The impact is really unexpected.
Each project manager have a rule to auto accept the hours.
each days, around 15 resources updates the hours and the hours should be
apply to the planning. So the project manager don't have to check the hours,
he want to see the actual by reports.
Question
The project manager can't pass the time to check if the resource did a wrong
thing or not.
How can I handle this?
Best regards,
Alexandre BARAULT