J
jpas1954
I am working with a number of project managers, each of whom does schedules
his or her own way. One of the things they are not good at is recording
actuals. About the most that they do is put percent complete. I am wondering
what the quickest way is to record actuals. I know you can set status date
and all that. But is there a way to record actuals that I could teach in a
short time to novice and experienced users? Can they save a baseline, and
just fill in actual start and actual finish? My fear is that it will all seem
too complex and they will abandon the method quickly. What do people
generally do in the real world to record actuals and maintain that against
the baseline?
his or her own way. One of the things they are not good at is recording
actuals. About the most that they do is put percent complete. I am wondering
what the quickest way is to record actuals. I know you can set status date
and all that. But is there a way to record actuals that I could teach in a
short time to novice and experienced users? Can they save a baseline, and
just fill in actual start and actual finish? My fear is that it will all seem
too complex and they will abandon the method quickly. What do people
generally do in the real world to record actuals and maintain that against
the baseline?