recording hours for resource with two cost rates under one task

G

Goldie

Could someone help me. I need to record acutal hours worked for one resource
that has two different cost rates for the two differnt roles they play under
one task.
 
D

Dale Howard [MVP]

Goldie --

There is no way to do this in Project Server in any version (2002, 2003, or
2007). When you assign a resource to a task, the software applies only one
Cost Rate, and the default rate is found on Cost Rate Table A. To change
the Cost Rate on the task, you can apply the Task Usage view, double-click
the resource's assignment on the task, and then select the desired Cost Rate
Table. You cannot select multiple Cost Rates on a single task, however.
Where you have erred is making the resource's assignment a single task. You
need to break up this task into two separate tasks, based on the type of
work the resource will do, and then specify the correct Cost Rate Table on
each task. Hope this helps.
 
G

Goldie

Thank you!!! Now I can stop banging my head on the computer trying to get it
to do something it cant.

g~
 
D

Dale Howard [MVP]

Goldie --

You are more than welcome for the help, my friend! Yes, please stop banging
your head on the computer; it's the only head you have. :)
 