Hi there,
I did a summary task that had 8 hours each month for a year and it showed
over 1000 hours of work. Does anyone have advice
Thanks a zillion
 
M

Mike Glen

Hi Jolie,

Welcome to this Microsoft Project newsgroup :)

The summary is showing the duration from the beginning of the first task to
the end of the last task. Doesn't make much sense in recurring tasks, but
that's how summaries work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen