Hi guys.
I need to know if there's a way to insert what I call a "Recurring Summary
Task", I mean, a set of tasks that repeat every certain time (weekly,
monthly..) and are linked between them.
I know I can insert a recurring task for each task of the set but I want to
have them as a whole set of tasks, like this
Summary Task
Summary Task 1
Task1 1
Task2 1
Summary Task 2
Task1 2
Task2 2
Do you know how could I do that?