I've set up a recurring Task in Project to reflect our daily sync meeting, 1
hour a day for 4 months. The pertinent details are below:
Duration: 1hr
Recurrence Pattern: Daily, Every 1 workday
Range of Recurrence: Start: Thu 1/7/10, End by: Fri 5/7/10
Calendar: Standard, Scheduling ignores resource calendars
The problem is that each person invited to this morning meeting is now
assigned 689h of Work time from this task alone. On the advice of another
person on this board, I set each meeting to Fixed Duration of 1hr each, but
this had no effect on the 689 hours. Can anyone tell me what I'm doing wrong?
hour a day for 4 months. The pertinent details are below:
Duration: 1hr
Recurrence Pattern: Daily, Every 1 workday
Range of Recurrence: Start: Thu 1/7/10, End by: Fri 5/7/10
Calendar: Standard, Scheduling ignores resource calendars
The problem is that each person invited to this morning meeting is now
assigned 689h of Work time from this task alone. On the advice of another
person on this board, I set each meeting to Fixed Duration of 1hr each, but
this had no effect on the 689 hours. Can anyone tell me what I'm doing wrong?