When I started to use Entourage, I thought that the recurrence pattern option "after the task is complete, create a new task every X d/w/m/y" was going to be great.

My problem is that it creates a new task from the due date, not from the completion date if the completion date is later than the due date.

If I wanted recurring tasks from the due date, I could simply set the task to recur every X d/w/m/y.

Is there a way to have Entourage generate a new task calculated from the actual completion date? Am I missing something somewhere?
 
W

William Smith

When I started to use Entourage, I thought that the recurrence
pattern option "after the task is complete, create a new task every X
d/w/m/y" was going to be great.

My problem is that it creates a new task from the due date, not from
the completion date if the completion date is later than the due
date.

If I wanted recurring tasks from the due date, I could simply set the
task to recur every X d/w/m/y.

Is there a way to have Entourage generate a new task calculated from
the actual completion date? Am I missing something somewhere?

Can you post an example of your recurring task specifying the fields and
settings you're using?

--

bill

William M. Smith, Microsoft Interop MVP - Mac/Windows
Entourage Help Page <http://entourage.mvps.org/>
Entourage Help Blog <http://blog.entourage.mvps.org/>
YouTalk <http://nine.pairlist.net/mailman/listinfo/youtalk>
 
B

Brenda

Example:

Task: Y
No start date
Due Date: July 1, 2008
No Reminder
Priority: Normal
Occurs: Custom Recurring Task: After task is complete, create a new task due in x d/w/m/y (let's say 10 days).
No end date.

Now let's say I complete the task on July 3. From the language used, I expected the task to recur on July 13 (10 days after the completed date. But when I checked the complete box, the task generated a new recurring entry for July 11(10 days after the due date).

Am I expecting too much from the program? Is there a way to have it calculate the recurrence from the completion date?
 
W

William Smith

Example:

Task: Y No start date Due Date: July 1, 2008 No Reminder Priority:
Normal Occurs: Custom Recurring Task: After task is complete, create
a new task due in x d/w/m/y (let's say 10 days). No end date.

Now let's say I complete the task on July 3. From the language used,
I expected the task to recur on July 13 (10 days after the completed
date. But when I checked the complete box, the task generated a new
recurring entry for July 11(10 days after the due date).

Am I expecting too much from the program? Is there a way to have it
calculate the recurrence from the completion date?

I'm reproducing your problem. Definitely looks like a bug or at minimum
poor wording if this is expected behavior.

Please be sure to let Microsoft know you'd like to see this fixed in
future versions by using the Help --> Send Feedback mechanism in any
Office application.

I will also escalate to Microsoft.

--

bill

William M. Smith, Microsoft Interop MVP - Mac/Windows
Entourage Help Page <http://entourage.mvps.org/>
Entourage Help Blog <http://blog.entourage.mvps.org/>
YouTalk <http://nine.pairlist.net/mailman/listinfo/youtalk>
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top