Using Project 2002 Pro, connected to Project Server. Added recurring tasks,
go to Calendar View, nothing shows. Checked View filter and All Tasks are
selected. Any idea why they don't show up?
 
D

Dale Howard [MVP]

Dean --

I do not believe that Recurring Tasks display in the Calendar view. To
confirm this, display the Calendar view for a project, then click Format -
Bar Styles. You will notice that Recurring Tasks are not on the list of bar
styles. Hope this helps.
 
J

JulieS

Hi Dean,

You can see the recurring tasks the calendar view in Project Professional if
the summary recurring task is expanded. From a Gantt view, click the Show
button in the Standard toolbar and choose All Subtasks. Change to the
Calendar view and you should be set.

As far as displaying in PWA, sorry, I can't help there.

I hope this helps.

Julie
 
D

Dale Howard [MVP]

Julie and Dean --

Julie, thanks for the correction. Dean, I apologize if I have wasted any of
your time or caused confusion for you.
 