When I insert a recurring task with a 2-hr duration and 12 occurrences (monthly meeting), why does it calculate the total duration to be over 200 days?
Duration is the number of days from the date the task is first scheduled to
the date the task is last scheduled.
Work is the actual number of hours the task will take during that duration.
JLB, PMP
Ted said:
When I insert a recurring task with a 2-hr duration and 12 occurrences
Yes, that's because the single recurring task line is, in fact, a summary of
all the recurring tasks. Click the little + sign to see all the tasks. You
can then modify each task individually if you wish.
Mike Glen
MS Project MVP