I'm trying to set up a weekly task that starts this Friday, is 15 minutes long, and occurs 20 times. Each time I do this I get a message saying 20 of 20 tasks will occur during norworking times. I'm given the option to reschedule them to the first working day, which I take, and Project makes them all start on the project start date - 4 Feb 2013.
I've done this before on a training room PC and it worked perfectly.
It makes no difference whether I choose a calendar for scheduling this task or not, nor scheduling ignores resource calendars.
I have set my work day to be 6 hours long, starting at 9am and stopping at 12 noon, and then restarting at 1pm and stopping at 4pm.
My work week is 30 hours long.
Has anyone else seen this? How can I fix it?
I've done this before on a training room PC and it worked perfectly.
It makes no difference whether I choose a calendar for scheduling this task or not, nor scheduling ignores resource calendars.
I have set my work day to be 6 hours long, starting at 9am and stopping at 12 noon, and then restarting at 1pm and stopping at 4pm.
My work week is 30 hours long.
Has anyone else seen this? How can I fix it?