RECURRING TASKS subtotal

D

DianneZ

In Project 2007 - when I set a recurring task such as a meeting for every
week, i get what I assume to be the elapsed time between the first and last
occurance of the recurring meeting. Can I get the summary task to show just
the total of all the meeting times IE if each meeting is 1 hour, and there
are 3 of them, 3 hours.
Currently it shows something like 72 hours!
Thank you
 
M

Mike Glen

Hi Dianne,

Welcome to this Microsoft Project newsgroup :)

No, this is one of the anomalies in Project .

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



In Project 2007 - when I set a recurring task such as a meeting for every
week, i get what I assume to be the elapsed time between the first and last
occurance of the recurring meeting. Can I get the summary task to show just
the total of all the meeting times IE if each meeting is 1 hour, and there
are 3 of them, 3 hours.
Currently it shows something like 72 hours!
Thank you
 
S

Steve House

This is due to the base definition of duration when applied to a summary
task ... the total amount of calendat working time between the start of the
earliest occuring subtask and the end of the latest finishing subtask. This
is true of all summary tasks, including the rolled-up representation of a
series of recurring tasks.
 