Pierre M
I have created dots for status indicators in the MSP 2003 custom Number1
field using the function IIf([% Work Complete]=100,"1",IIf([Finish]<[Current
Date],"2","3")) This works fine for all the subtasks and mirrors the MSP
"Status Indicator" field but it doesn't roll-up to the parent task. The MSP
"Status Indicator" field does roll-up nicely and I would like to mirror that
performance. Any help would be greatly appreciated.