S
Shaun
Here is my scenario. I have a task that was scheduled
for 50 hours. I have 2 engineers assigned to the task
(200% units). My calandar is set up for a 32 hour work
week (80% utilization) which makes my duration 6.02
days. The task is set as effort driven/fixed units. To
date, between the 2 engineers, they have worked 23 hours
on this task leaving me 27 hours remaining. One of my
engineers has been transfered off to a new job. I
changed my Max. Units in the Resource Sheet to 100%. I
then changed the number of units in the task to 100%.
This should have increased my duration on the task by
another day or so to account for 1 resource working the
remaining 27 hours, however my duration does not change
at all. Also when I click "Level Now" it returns the
resources to 200% and maintains the original 6.02 day
duration. Is this because we have started the task? Is
there a way I can get Project to calculate my new
duration correctly with out zeroing out the actual work?
Thank you,
Shaun Kenney
for 50 hours. I have 2 engineers assigned to the task
(200% units). My calandar is set up for a 32 hour work
week (80% utilization) which makes my duration 6.02
days. The task is set as effort driven/fixed units. To
date, between the 2 engineers, they have worked 23 hours
on this task leaving me 27 hours remaining. One of my
engineers has been transfered off to a new job. I
changed my Max. Units in the Resource Sheet to 100%. I
then changed the number of units in the task to 100%.
This should have increased my duration on the task by
another day or so to account for 1 resource working the
remaining 27 hours, however my duration does not change
at all. Also when I click "Level Now" it returns the
resources to 200% and maintains the original 6.02 day
duration. Is this because we have started the task? Is
there a way I can get Project to calculate my new
duration correctly with out zeroing out the actual work?
Thank you,
Shaun Kenney