We have a serious problem here. Why for a given project, in a given task
with actuals, when we reduce the duration of the task the actual of some
ressources are reducing to. Actuals should be protected data.
For example, I have this task with these specifications :
BEFORE the duration is changed
Task : Detail Stakeholder Requirements
Start : Wed 05-04-13
Finish : Mon 05-08-29
Duration : 6,14d days
Ressource 1 : 28 h of actual work
AFTER the duration is changed
Task : Detail Stakeholder Requirements
Start : Wed 05-04-13
Finish : Fri 05-04-15
Duration : 2 days
Ressource 1 : 9 h of actual work
Why does't it make this automatic calculation?
Andrea
We have a serious problem here. Why for a given project, in a given task
with actuals, when we reduce the duration of the task the actual of some
ressources are reducing to. Actuals should be protected data.
For example, I have this task with these specifications :
BEFORE the duration is changed
Task : Detail Stakeholder Requirements
Start : Wed 05-04-13
Finish : Mon 05-08-29
Duration : 6,14d days
Ressource 1 : 28 h of actual work
AFTER the duration is changed
Task : Detail Stakeholder Requirements
Start : Wed 05-04-13
Finish : Fri 05-04-15
Duration : 2 days
Ressource 1 : 9 h of actual work
Why does't it make this automatic calculation?
Andrea