Reducing Resources to be less than 100%

J

JPD

I have a schedule put together about 500lines. We have laid out the
plan and resourcing with fixed durations non effort driven.

A lot of the resourcing is loaded at 100%. In out mind no resource is
ever at 100% when you take into consideration vacation, sick time,
training , etc. We would like to make a "global" change to say no
resource is ever really over 90% allocated on a task. Without
changing the durations etc.

Is there a way to do this without looking at each task and reducing
the % allocated ????

Thanks for your help in advance.

~J
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top