J
Jac
hi,
The Tracking Table in Tracking Gantt view has a column named Physical %
Completed, this column's values will not be reflected on the Tracking Gantt
as what % Completed would; is there any way to reflect the Physical %
Completed values on Tracking Gantt?
Another thing is if 50% lag time is added in a duration, the start time &
finish time changed to 1:00pm & 12:00pm respectively. But why if 40% lag time
is added, the start time & finish time changed to 9:36am & 9:36am
respectively (seem to base on 24 hours)? is it because the start time is no
longer based on the Standard Calendar?
Thanks!
The Tracking Table in Tracking Gantt view has a column named Physical %
Completed, this column's values will not be reflected on the Tracking Gantt
as what % Completed would; is there any way to reflect the Physical %
Completed values on Tracking Gantt?
Another thing is if 50% lag time is added in a duration, the start time &
finish time changed to 1:00pm & 12:00pm respectively. But why if 40% lag time
is added, the start time & finish time changed to 9:36am & 9:36am
respectively (seem to base on 24 hours)? is it because the start time is no
longer based on the Standard Calendar?
Thanks!