Hi;
I'm using MSP professional 2003 ....
There are situations when a project is endorsed in a phased approach... a
project plan may have 3 phases and only one is endorsed. for the other two
phases, resources are identified but the timelines are not endorsed.
Project plan is connected to a master resource pool. I'd like to see the
impact of resources' availibility in resource pool with a distinction of
resource's allocation with timelines for phase 2 and 3 shwoing proposed
booking.
I can not make the resource as proposed using the resource information tab
as the same resource is being used for phase 1. is there a work around that
I can use to show a resource's tentative / proposed assignment for a project
in resource pool?
and no I do not have project central server...
I'm using MSP professional 2003 ....
There are situations when a project is endorsed in a phased approach... a
project plan may have 3 phases and only one is endorsed. for the other two
phases, resources are identified but the timelines are not endorsed.
Project plan is connected to a master resource pool. I'd like to see the
impact of resources' availibility in resource pool with a distinction of
resource's allocation with timelines for phase 2 and 3 shwoing proposed
booking.
I can not make the resource as proposed using the resource information tab
as the same resource is being used for phase 1. is there a work around that
I can use to show a resource's tentative / proposed assignment for a project
in resource pool?
and no I do not have project central server...