Refresh my memory - Project Pro 2003 - Calendars

R

radman57

Hello:

Its been awhile, but I can't remember if after you change a project
base Calendar to a different one using the Project>Project
Information> Project Calendar setting, Do I have to go back and change
existing tasks that were created before the Calendar change to use the
newer Project setting in the "Task calendar" column?
 
J

Jan De Messemaeker

Hi,

Tasks without a task calendar and without resourcs use the >Project Calndar,
and when you change the prohe-ject calendar, theit schedule adapts
automatically.

OTOH, if your tasks did have a task calendar, you cwill have to change that
one.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 