R
Rene
Hi Anyone;
I'm about to roll out PS timesheets to our organization and I see in
Admin>Customize Project Web Access>Manage Timesheet Periods that the
existing Start and Finish dates are incorrect. I cannot change nor
delete them. I can add or insert the correct Start and Finish dates
but this generates a "Gap" error when a "check" is performed. I need
to change or delete these dates to initiate this roll out - Please
Help!!
Environment:
We have not officially rolled out PS. There are 25 current PS projects
that we've been playing with. Some have actuals that may have occurred
during a short period when the Managed Timesheet Period was enabled.
How do I restart the managed timesheet periods without losing
unofficial existing project data.
Thanks to anyone,
Rene
I'm about to roll out PS timesheets to our organization and I see in
Admin>Customize Project Web Access>Manage Timesheet Periods that the
existing Start and Finish dates are incorrect. I cannot change nor
delete them. I can add or insert the correct Start and Finish dates
but this generates a "Gap" error when a "check" is performed. I need
to change or delete these dates to initiate this roll out - Please
Help!!
Environment:
We have not officially rolled out PS. There are 25 current PS projects
that we've been playing with. Some have actuals that may have occurred
during a short period when the Managed Timesheet Period was enabled.
How do I restart the managed timesheet periods without losing
unofficial existing project data.
Thanks to anyone,
Rene