Reject a task assigment in PWA 2007

N

Noe

In Project Web Access 2003…
When you receive new task assignments, they are marked with the new
assignment icon in the indicators column. If it’s necessary for you to reject
an assignment, you can follow these steps:
1 In the Timesheet view or Gantt Chart, click the assignment in the table.
2 Above the table, click Reject and then click Yes.
The assignment is removed from your Tasks list, and an update is submitted
for the project manager. The project manager will then review the rejection.
If the project manager accepts the rejected assignment, your name is removed
as an assigned resource on this task in the project plan.

How this would be done in PWA 2007?

Thanks,
Noe Cabrera
 
D

Dave

It is normally preferred that questions relating to Project Server are
asked on microsoft.public.project.server.
 
D

Dale Howard [MVP]

Noe --

In the future, please post your Project Server 2007 questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
tell the team member to do the following:

1. Log into PWA and navigate to the My Tasks page.
2. Select the option checkbox to the left of the task he/she wishes to
reject.
3. Click the Actions pick list button and choose the Delete item on the
pick list.
4. When prompted for confirmation, click the OK button.
5. Click the Submit Selected button.

The system will send the PM a Delete Assignment Request on the Task Updates
page in PWA. When the PM approves the request, then updates and republishes
the project, the deleted task will disappear from the team member's My Tasks
page. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top