N
Noe
In Project Web Access 2003…
When you receive new task assignments, they are marked with the new
assignment icon in the indicators column. If it’s necessary for you to reject
an assignment, you can follow these steps:
1 In the Timesheet view or Gantt Chart, click the assignment in the table.
2 Above the table, click Reject and then click Yes.
The assignment is removed from your Tasks list, and an update is submitted
for the project manager. The project manager will then review the rejection.
If the project manager accepts the rejected assignment, your name is removed
as an assigned resource on this task in the project plan.
How this would be done in PWA 2007?
Thanks,
Noe Cabrera
When you receive new task assignments, they are marked with the new
assignment icon in the indicators column. If it’s necessary for you to reject
an assignment, you can follow these steps:
1 In the Timesheet view or Gantt Chart, click the assignment in the table.
2 Above the table, click Reject and then click Yes.
The assignment is removed from your Tasks list, and an update is submitted
for the project manager. The project manager will then review the rejection.
If the project manager accepts the rejected assignment, your name is removed
as an assigned resource on this task in the project plan.
How this would be done in PWA 2007?
Thanks,
Noe Cabrera