V
VJ
We are using MS office Project 2003/SP3 and SQL2005 database. This is been happning to multiple users
Resource Enters 40 hours(8 hours a day) for a Task and submits it.
Project Managers Rejects the 40 hours for the resource.
When the Resource opens the PWA (Project Web Access), Resource doesn't see any hours in PWA (Resource should have seen 40 hours that were rejected)
In PWA Actuals Hours shows 40 hours and Remaining Hours as 40 hours, After PM rejected the hours, it should have shown Actual Hours as 80 and Remaining hours as 0
Any help on this would be greatly appreciated
Thanks
Resource Enters 40 hours(8 hours a day) for a Task and submits it.
Project Managers Rejects the 40 hours for the resource.
When the Resource opens the PWA (Project Web Access), Resource doesn't see any hours in PWA (Resource should have seen 40 hours that were rejected)
In PWA Actuals Hours shows 40 hours and Remaining Hours as 40 hours, After PM rejected the hours, it should have shown Actual Hours as 80 and Remaining hours as 0
Any help on this would be greatly appreciated
Thanks