A
AmWall
I am using Project Server 2007 pre-SP1.
We have a large number of tasks that are showing up in the Tasks results
indicating they are rejected for invalid data. The PM's have created Manage
Rules that Approve all Task updates.
On another note we are having problems with PMs that are only Saving changes
to the project plan not Publishing the changes then other PMs opening the
same Project updating the plan Saving and not Publishing. I think this is
creating problems with the integrity of the Project and that the changes
should be Published. The reasoning behind not publishing is that they do not
want the Resources receiving email notifications constantly regarding task
updates.
Would this behavior have something to do with the first problem?
How do we fix the rejected, or find out what is rejecting them?
Thanks
Margaret
We have a large number of tasks that are showing up in the Tasks results
indicating they are rejected for invalid data. The PM's have created Manage
Rules that Approve all Task updates.
On another note we are having problems with PMs that are only Saving changes
to the project plan not Publishing the changes then other PMs opening the
same Project updating the plan Saving and not Publishing. I think this is
creating problems with the integrity of the Project and that the changes
should be Published. The reasoning behind not publishing is that they do not
want the Resources receiving email notifications constantly regarding task
updates.
Would this behavior have something to do with the first problem?
How do we fix the rejected, or find out what is rejecting them?
Thanks
Margaret