M
Mary
Hello
When a team member goes into Project Web Access and rejects a task - the
Project Manager gets an email informing them.
The Project Manager then goes into Project Web Access and accepts the
rejection. This all works fine - and the rejected task is removed from the
Team Members task list in Project Web Access.
However, the Project Manager is then prompted to save the Project plan -
which he does but the resource listed on the Project plan is still the team
member who had rejected that task assignement.
So basically, Project isn't updating.
The problem with this is - when the Project Manager goes to publish - the
Team Member who originally rejected the task gets it appearing back in their
task list on Project Web Access. (which isn't good).
Is this supposed to work like this - or am I missing something?
Thanks!
When a team member goes into Project Web Access and rejects a task - the
Project Manager gets an email informing them.
The Project Manager then goes into Project Web Access and accepts the
rejection. This all works fine - and the rejected task is removed from the
Team Members task list in Project Web Access.
However, the Project Manager is then prompted to save the Project plan -
which he does but the resource listed on the Project plan is still the team
member who had rejected that task assignement.
So basically, Project isn't updating.
The problem with this is - when the Project Manager goes to publish - the
Team Member who originally rejected the task gets it appearing back in their
task list on Project Web Access. (which isn't good).
Is this supposed to work like this - or am I missing something?
Thanks!