RELATE MAT'L & WORK RSRCS TO DEMONSTRATE PRODUCTIVITY RATE

P

pablo5

using project 2003 standard - would like to be able to relate material and
work resources to demonstrate productivity rate and calculate units, work and
duration accordingly. For an example, if my task is 'pain room', and I
utilize a material resource (paint) and a work resource (painter), suppose a
painter paints at a rate of .5 gallon per hour. When I enter that my
material requirements are 100 gallons of paint, I would like to see the
software be able to automatically assign the painter to the task and
calculate that the assignment is 200 hours of work

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...6d547fb&dg=microsoft.public.project.developer
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top